Górażdze Cement S.A. scrap trap between the elevator and the separator of the closed cement mill No. 3.

» Notice description

Nazwa: Trap
Opis:
Ilość: 1 [szt.]

Wymagania dodatkowe:
Payments conditions (Required minimum 90 days)
Delivery terms (Required DDP plant Górażdże Cement S.A)
Guarantee terms (Required minimum 24 months)
Delivery time (till 15.01.2020)
List of spare and wear parts for 3 years of operation ()
offer_value (Wartość oferty)
Total price ()

Opis i specyfikacja:

On behalf of Gorazdze Cement S.A., a member of the global Heidelberg Cement Group, you are invited to present your offer for:
Scrap trap between the elevator and the separator of the closed cement mill No. 3.

1) Technical characteristics of conveyors and transported material:
Slide width: 500 mm
Slide length: 10 500mm
Aeration fabric: B585
Performance: max. 450 t / h

2. Scope of delivery:
• Issuing guidelines for the implementation of the project,
• supporting structure,
• Chute for scrap metal to level "0" as an option,
• Container for separated scrap of about 1.5 m3,
• Any additional OHS covers restricting access to moving parts
• Separator control cabinet as an option,
• Mechanical assembly and commissioning supervision as an option

3. The offer should include:
• dimensional drawing,
• description of individual elements, materials used,
• price for the range above,
• the price of spare and quick-wear parts for a period of 3 years,
• delivery time from the moment the order is placed,
• terms of delivery and payment,• guarantees,
A site visit is required before submitting an offer.
Enclosures:
1 - 3 pcs od drawings.


Delivery time 15.01.2020
Contact persons from Górażdze Cement S.A. site : Zbigniew Szyszka 77 777 8406 or . +48 693839 560

Make an offer


» Time limit for receipt of tenders

27.09.2019 | 12:00


» Location



» Category assortment